Tags

Authors

Date

.

Relevant Novologic Module​

Alphanumeric Naming Convention (also Schedule File Name Convention)

by | May 1, 2023 | Blogs, Insights | 0 comments

Illustration 3.2 Schedule file name convention for identification of schedule versions
Month Month & Year Schedule Version Data Date Print Date (Publish Date) Substantial Completion (MS85) Slippage Note
0 Aug 2021 0-A Contractor’s Draft Schedule 2021-09-13 (assumed data date) 2021-09-07 2023-12-29
  •  Contractor’s Draft Schedule. Submitted by Percon on 2021-09-07.
  •  Data Date was not specified in source data (Microsoft Project schedule PDF file), and has been assumed to be 2021-09-13 as it was the start date of the first activity in this schedule version.
0 Aug 2021 0-B Contractor’s Draft Schedule 2021-10-04 (assumed data date) 2021-10-05 2023-12-29
  • Contractor’s Baseline Schedule. Submitted by Percon on 2021-10-05.
  •  Data Date was not specified in source data (Microsoft Project schedule PDF file), and has been assumed to be 2021-10-04 as it was the start date of the first activity in this schedule version.
1 Sep 2021
2 Oct 2021
3 Nov 2021 3-C Schedule Update 2021-11-12 (assumed data date) 2021-11-12 2024-02-14 🔺-48 cd 🔺-33 wd
  • Schedule version 3-C, submitted by Percon. First schedule submission for Nov 2021. Data Date was moved to 2021-11-12
  • Did not show any progress since the start of the project.
  • Showed delay due to contaminated fill.
3 Nov 2021 3-D Schedule Update 2021-11-26 (assumed data date) 2021-11-26 2024-02-23 🔺-57 cd 🔺-393 wd
  • Schedule version 3-D, submitted by Percon. Second schedule submission for Nov 2021. Data Date was moved to 2021-11-26.
  • Did not show any progress since the start of the project.
  • Showed delay due to contaminated fill.
4 Dec 2021
5 Jan 2022
6 Feb 2022 6-D Schedule Update 2022-02-10 (assumed data date) 2022-02-10 2024-04-08 🔺-102 cd 🔺-69 wd
  • Schedule version 6-D, submitted by Percon. Data Date was moved to 2022-02-10.
  • Showed delay due to contaminated fill.
  • ⛔ Schedule version 6-D incorrectly showed the start date of parking garage excavation to be 2021-12-13 A – but this activity actually started on 2021-11-09.
7 March 2022
8 April 2022 8-D Schedule Update 2022-04-11 (assumed data date) 2022-04-21 2024-05-03 🔺-127 cd 🔺-88 wd
  • Schedule version 8-D, submitted by Percon. Data Date was moved to 2022-04-11
  • Showed delay in parking garage forming due to strike of truckers / haulers in late Mar 2022, and early Apr 2022.
  • ⛔ No cancellation of concrete delivery, or concrete pour was reported for the referenced period.
9 May 2022
10 June 2022 10-D Schedule Update 2022-06-24 (assumed data date) 2022-06-30 2024-07-04 🔺-189 cd 🔺-130 wd
  • Schedule version 10-D, submitted by Percon. Data Date was moved to 2022-06-24
  • Schedule version (8-D) shows delay in parking garage forming due to strike of truckers / haulers in late Mar 2022, and early Apr 2022.
  • ⛔ In a span of 135 cd (between versions 6-D and 10-D), the Substantial Completion milestone experienced a delay of 87 cd. This demonstrates that the total actual schedule progress was 50% lower than the total planned schedule progress – and there were schedule slippages in addition to the delay causes cited by Percon.
11 July 2022
12 Aug 2022
13 Sep 2022
14 Oct 2022
15 Nov 2022 15-D Schedule Update 2022-11-08 (assumed data date) 2022-11-17 2024-08-27 🔺-243 cd 🔺-168 wd
  • Schedule version 15-D, submitted by Percon. Data Date was moved to 2022-11-08.
  • In version 15-D, an additional delay of 54 cd to the Substantial Completion milestone was reported by Percon.
16 Dec 2022
17 Jan 2022 17-D Schedule Update 2023-01-30 (assumed data date) 2023-02-09 2024-07-24 🔺-209 cd 🔺-144 wd
  • Schedule version 17-D, submitted by Percon. Data Date was moved to 2023-01-30
  • As of version 17-D, the total delay to the Substantial Completion milestone was equal to 209 cd. However, about 34 cd of schedule gain (delay mitigation) was reported by Percon

0 Comments

Trackbacks/Pingbacks

  1. Lexicon - Stoneboy - […] Alphanumeric Naming Convention is a convenient format to monitor the number of schedule submissions, schedule version history, and version…

Submit a Comment

Related Tags :