Lexicon & Good Practices

A list of terms, keywords, abbreviations, and acronyms used in reporting system.

Data Formats

Types of Duration in Scheduling

Schedule Version

An umbrella term for a schedule submission such as a baseline schedule, a schedule update, a recovery schedule, or a scenario planning schedule.

Variation

Delay

Delay Analysis Methodology

Schedule Versions

Reference information for schedule version number, and names is provided below.

Alphanumeric Naming Convention (also Schedule File Name Convention)
Illustration 3.2 Schedule file name convention for identification of schedule versions
Month Month & Year Schedule Version Data Date Print Date (Publish Date) Substantial Completion (MS85) Slippage Note
0 Aug 2021 0-A Contractor’s Draft Schedule 2021-09-13 (assumed data date) 2021-09-07 2023-12-29
    Contractor’s Draft Schedule. Submitted by Percon on 2021-09-07.
  •  Data Date was not specified in source data (Microsoft Project schedule PDF file), and has been assumed to be 2021-09-13 as it was the start date of the first activity in this schedule version.
0 Aug 2021 0-B Contractor’s Draft Schedule 2021-10-04 (assumed data date) 2021-10-05 2023-12-29
  • Contractor’s Baseline Schedule. Submitted by Percon on 2021-10-05.
  •  Data Date was not specified in source data (Microsoft Project schedule PDF file), and has been assumed to be 2021-10-04 as it was the start date of the first activity in this schedule version.
1 Sep 2021
2 Oct 2021
3 Nov 2021 3-C Schedule Update 2021-11-12 (assumed data date) 2021-11-12 2024-02-14 🔺-48 cd 🔺-33 wd
  • Schedule version 3-C, submitted by Percon. First schedule submission for Nov 2021. Data Date was moved to 2021-11-12
  • Did not show any progress since the start of the project.
  • Showed delay due to contaminated fill.
3 Nov 2021 3-D Schedule Update 2021-11-26 (assumed data date) 2021-11-26 2024-02-23 🔺-57 cd 🔺-393 wd
  • Schedule version 3-D, submitted by Percon. Second schedule submission for Nov 2021. Data Date was moved to 2021-11-26.
  • Did not show any progress since the start of the project.
  • Showed delay due to contaminated fill.
4 Dec 2021
5 Jan 2022
6 Feb 2022 6-D Schedule Update 2022-02-10 (assumed data date) 2022-02-10 2024-04-08 🔺-102 cd 🔺-69 wd
  • Schedule version 6-D, submitted by Percon. Data Date was moved to 2022-02-10.
  • Showed delay due to contaminated fill.
  • â›” Schedule version 6-D incorrectly showed the start date of parking garage excavation to be 2021-12-13 A – but this activity actually started on 2021-11-09.
7 March 2022
8 April 2022 8-D Schedule Update 2022-04-11 (assumed data date) 2022-04-21 2024-05-03 🔺-127 cd 🔺-88 wd
  • Schedule version 8-D, submitted by Percon. Data Date was moved to 2022-04-11
  • Showed delay in parking garage forming due to strike of truckers / haulers in late Mar 2022, and early Apr 2022.
  • â›” No cancellation of concrete delivery, or concrete pour was reported for the referenced period.
9 May 2022
10 June 2022 10-D Schedule Update 2022-06-24 (assumed data date) 2022-06-30 2024-07-04 🔺-189 cd 🔺-130 wd
  • Schedule version 10-D, submitted by Percon. Data Date was moved to 2022-06-24
  • Schedule version (8-D) shows delay in parking garage forming due to strike of truckers / haulers in late Mar 2022, and early Apr 2022.
  • â›” In a span of 135 cd (between versions 6-D and 10-D), the Substantial Completion milestone experienced a delay of 87 cd. This demonstrates that the total actual schedule progress was 50% lower than the total planned schedule progress – and there were schedule slippages in addition to the delay causes cited by Percon.
11 July 2022
12 Aug 2022
13 Sep 2022
14 Oct 2022
15 Nov 2022 15-D Schedule Update 2022-11-08 (assumed data date) 2022-11-17 2024-08-27 🔺-243 cd 🔺-168 wd
  • Schedule version 15-D, submitted by Percon. Data Date was moved to 2022-11-08.
  • In version 15-D, an additional delay of 54 cd to the Substantial Completion milestone was reported by Percon.
16 Dec 2022
17 Jan 2022 17-D Schedule Update 2023-01-30 (assumed data date) 2023-02-09 2024-07-24 🔺-209 cd 🔺-144 wd
  • Schedule version 17-D, submitted by Percon. Data Date was moved to 2023-01-30
  • As of version 17-D, the total delay to the Substantial Completion milestone was equal to 209 cd. However, about 34 cd of schedule gain (delay mitigation) was reported by Percon
 