| Month |
Month & Year |
Schedule Version |
Data Date |
Print Date
(Publish Date) |
Substantial Completion (MS85) |
Slippage |
Note |
| 0 |
Aug 2021 |
0-A
Contractor’s Draft Schedule |
2021-09-13
(assumed data date) |
2021-09-07 |
2023-12-29 |
|
- Contractor’s Draft Schedule. Submitted by Percon on 2021-09-07.
- Â Data Date was not specified in source data (Microsoft Project schedule PDF file), and has been assumed to be 2021-09-13 as it was the start date of the first activity in this schedule version.
|
| 0 |
Aug 2021 |
0-B
Contractor’s Draft Schedule |
2021-10-04
(assumed data date) |
2021-10-05 |
2023-12-29 |
|
- Contractor’s Baseline Schedule. Submitted by Percon on 2021-10-05.
- Â Data Date was not specified in source data (Microsoft Project schedule PDF file), and has been assumed to be 2021-10-04 as it was the start date of the first activity in this schedule version.
|
| 1 |
Sep 2021 |
|
|
|
|
|
|
| 2 |
Oct 2021 |
|
|
|
|
|
|
| 3 |
Nov 2021 |
3-C
Schedule Update |
2021-11-12
(assumed data date) |
2021-11-12 |
2024-02-14 |
🔺-48 cd
🔺-33 wd |
- Schedule version 3-C, submitted by Percon. First schedule submission for Nov 2021. Data Date was moved to 2021-11-12
- Did not show any progress since the start of the project.
- Showed delay due to contaminated fill.
|
| 3 |
Nov 2021 |
3-D
Schedule Update |
2021-11-26
(assumed data date) |
2021-11-26 |
2024-02-23 |
🔺-57 cd
🔺-393 wd |
- Schedule version 3-D, submitted by Percon. Second schedule submission for Nov 2021. Data Date was moved to 2021-11-26.
- Did not show any progress since the start of the project.
- Showed delay due to contaminated fill.
|
| 4 |
Dec 2021 |
|
|
|
|
|
|
| 5 |
Jan 2022 |
|
|
|
|
|
|
| 6 |
Feb 2022 |
6-D
Schedule Update |
2022-02-10
(assumed data date) |
2022-02-10 |
2024-04-08 |
🔺-102 cd
🔺-69 wd |
- Schedule version 6-D, submitted by Percon. Data Date was moved to 2022-02-10.
- Showed delay due to contaminated fill.
- â›” Schedule version 6-D incorrectly showed the start date of parking garage excavation to be 2021-12-13 A – but this activity actually started on 2021-11-09.
|
| 7 |
March 2022 |
|
|
|
|
|
|
| 8 |
April 2022 |
8-D
Schedule Update |
2022-04-11
(assumed data date) |
2022-04-21 |
2024-05-03 |
🔺-127 cd
🔺-88 wd |
- Schedule version 8-D, submitted by Percon. Data Date was moved to 2022-04-11
- Showed delay in parking garage forming due to strike of truckers / haulers in late Mar 2022, and early Apr 2022.
- â›” No cancellation of concrete delivery, or concrete pour was reported for the referenced period.
|
| 9 |
May 2022 |
|
|
|
|
|
|
| 10 |
June 2022 |
10-D
Schedule Update |
2022-06-24
(assumed data date) |
2022-06-30 |
2024-07-04 |
🔺-189 cd
🔺-130 wd
|
- Schedule version 10-D, submitted by Percon. Data Date was moved to 2022-06-24
- Schedule version (8-D) shows delay in parking garage forming due to strike of truckers / haulers in late Mar 2022, and early Apr 2022.
- â›” In a span of 135 cd (between versions 6-D and 10-D), the Substantial Completion milestone experienced a delay of 87 cd. This demonstrates that the total actual schedule progress was 50% lower than the total planned schedule progress – and there were schedule slippages in addition to the delay causes cited by Percon.
|
| 11 |
July 2022 |
|
|
|
|
|
|
| 12 |
Aug 2022 |
|
|
|
|
|
|
| 13 |
Sep 2022 |
|
|
|
|
|
|
| 14 |
Oct 2022 |
|
|
|
|
|
|
| 15 |
Nov 2022 |
15-D
Schedule Update |
2022-11-08
(assumed data date) |
2022-11-17 |
2024-08-27 |
🔺-243 cd
🔺-168 wd
|
- Schedule version 15-D, submitted by Percon. Data Date was moved to 2022-11-08.
- In version 15-D, an additional delay of 54 cd to the Substantial Completion milestone was reported by Percon.
|
| 16 |
Dec 2022 |
|
|
|
|
|
|
| 17 |
Jan 2022 |
17-D
Schedule Update |
2023-01-30
(assumed data date) |
2023-02-09 |
2024-07-24 |
🔺-209 cd
🔺-144 wd |
- Schedule version 17-D, submitted by Percon. Data Date was moved to 2023-01-30
- As of version 17-D, the total delay to the Substantial Completion milestone was equal to 209 cd. However, about 34 cd of schedule gain (delay mitigation) was reported by Percon
|